Welcome to

Bath Borough

Northampton County, PA

State Route 248 (W. Northampton Street) Re-Alignment Project: Construction to Begin Mid-2024

Last modified:
June 7, 2024 10:56 am

By: Brad Flynn | Published March 12, 2024

Construction for the State Route 248 re-alignment project in Bath Borough is moving forward mid-2024! This project has been in the planning phase for more than two decades. Through all the public discussions, planning/design, and tested patience, a massive piece to the Borough’s transportation improvement plan is finally falling into place!

During the regular Council meeting of Monday, March 11th, Mr. Michael McGuire, P.E. Consultant Project Manager of the Pennsylvania Department of Transportation Engineering District 5-0 provided Council and the public with the latest status update regarding the 248-re-alignment project. The project includes re-alignment of the W. Northampton Street and W. Main Street intersection, a full bridge replacement, and reconstruction of W. Northampton Street from the bridge to Chestnut Street. State Route 248 will then re-align from Chestnut Street, following W. Northampton Street to W. Main Street. Construction is expected to begin during the summer of 2024 lasting two to three years. The timeline of construction phasing will be largely dependent on weather conditions over the next few years.

Residents, business owners, and those affected by the upcoming construction are asked to please be patient. When the bridge replacement phase begins (sometime in 2025) there is likely to be heavy traffic congestion and delays. As painful as the construction phases will be, we need to remember the end game. Bath is finally receiving significant transportation improvements that will make it a bit easier for traffic to flow in and out of town. Start planning now for anticipated traffic congestion and delays. Think about alternative routes around Bath.

IMPORTANT NOTE

If, during the re-alignment construction, you have a public safety or traffic concern you would like to share with the PennDOT Construction Project Superintendent, please pass along those concerns to Borough Manager Brad Flynn. You may email Manager Flynn (manager@boroughofbath.org) or call the office (610) 837-6525.

THANK YOU!

The Borough of Bath wishes to thank Mike McGuire, P.E. and the entire PennDOT District 5-0 team for helping not only the Bath community, but the surrounding area, with this significant transportation improvement. Bath wants to acknowledge Keystone Consulting Engineers for their work in developing the Borough’s Master Long Range Transportation Improvement Plan, providing PennDOT additional research that strengthen re-alignment concepts into reality. The Borough is also grateful for the efforts of former PA State Senator Mario Scavello and former PA State Representative Marcia Hahn guiding state and federal resources toward the Bath 248 re-alignment project over the years.

The 248-re-alignment project has an overall cost estimate north of $6 million. The financial resources for this project are proportioned between federal and state dollars (80/20 respectively).


PennDOT PowerPoint

Here is a copy of the PennDOT presentation discussed on March 11th, 2024:


PennDOT State Route 248 Re-alignment Presentation

If you couldn’t attend the March 11th Council Meeting for the details about the 248 re-alignment, please watch the video below:


Questions & Answers Section (Public Questions during the March 11th Meeting)

When the public utilities are relocated, what would be the downtime for customers?

Downtown should be minimal. For example, electric utility relocation requires moving poles and relocating overhead power lines. The actual relocation of power lines could take 2 days (weather permitting). Affected customers will receive advance notice (14 days) prior to utility service disruption.

What’s happening with State Route 329 at W. Main Street during the re-alignment construction?

As of now, there are no plans to install a temporary traffic signal at State Route 329 and W. Main Street during the re-alignment project. PennDOT will evaluate conditions at this intersection. PennDOT and the Borough to report public safety concerns/issues that may arise by contacting the Borough Office (610) 837-6525 or emailing Borough Manager Brad Flynn (manager@boroughofbath.org).

What is the timelines for reconstruction of W. Northampton Street and how long could the segment of W. Northampton Street (from the bridge to Chestnut Street) be closed for?

Construction work for the re-alignment project will be coordinated at one time (as best as possible). There will be access to individual property owners. No one will be cut-off from W. Northampton Street. EXCEPTION: When the bridge replacement project begins, the bridge will be closed. Bridge closure could last 9 months. Reconstruction of W. Northampton Street could run between 4 to 6 weeks. All of the re-alignment construction work is dependent on weather conditions.

How are school buses going to handle traffic issues and getting kids to school?

There will be access through W. Northampton Street until the W. Northampton Street bridge is closed. Alternate routes will be explored by the school district. School district officials are aware of the re-alignment project and associated timelines of construction. W. Main Street and W. Northampton Street will not be closed at the same time.

With the re-alignment of W. Northampton Street into W. Main Street, when complete, will this increase the speed of traffic in that area?

The intersection will be expanded, forming a new triangle with designated turning lanes and through lanes. Traffic will continually move at a slower pace during construction. W. Northampton Street traffic will be required to yield once merging onto W. Main Street, but there will be a designated merge lane once the construction is complete. At this time, there are no plans to signalize the re-alignment intersection.

Will there be any advanced warning signalization outside of Bath prior to the construction area?

There will be construction signage but nothing in addition to what will normally be required on a project like this. The construction zones will be down to 25 mph. There will be detour routes established once the W. Northampton Street bridge closure commences.

There are already traffic issues on Green Street because motorists try to avoid the Race Street//Main Street intersection. The re-alignment project is likely to make the problems worse. Green Street is narrow, and residents can only park on one side of the street. Is there anything being considered to improve traffic concerns along Green Street?

There are no plans, at this time, to review Green Street traffic. The construction project, while ongoing, may not improve matters, Green Street traffic should improve once the re-alignment project is complete.

Is there any chance that the public utilities (overhead utilities) can be placed underground, or will utility poles and overhead wires remain?

Public overhead utilities will remain as they are, overhead and on utility poles; Met-Ed and Verizon.

When you close Old Forge Drive, there is no ADA access at the intersection with Creek Road. Will PennDOT fix ADA issues in the area of Old Forge Drive and Creek Road?

Old Forge Drive will not be closed during construction. Sidewalk and ADA issues near Old Forge Drive and Creek Road are not within the construction scope of the current re-alignment project.

If roadways are going to be closed and traffic is going to be re-routed, is PennDOT going to repave those roadways because of the increased traffic? What about potholes from the increased traffic, will PennDOT take care of these issues?

State roadways are part of PennDOT’s normal paving cycle. Some roadways within the construction area will be repaired and replaced. Potholes associated with construction will be repaired. Any other roadway issues that are not within the PennDOT right-of-way will be handled by the Borough.

Is PennDOT considering an inlet on the south side of W. Northampton Street, east of the unnamed alley in the 200 block of W. Northampton Street?

There will be storm water inlets on W. Northampton Street as there currently is.

Parking concerns: The public parking lot across from Villa Grande, half of the parking lot will be occupied with PennDOT construction equipment and materials. Will there be parking alleviations or any recommendations on parking around the 200 block of W. Northampton Street?

PennDOT would advise the Borough to alleviate parking restrictions during construction and especially during the bridge closure. Unfortunately, there are not many parking options, and the construction phase will not improve matters. The Borough’s Public Safety Committee will look into temporarily suspending some parking regulations in and around the construction area in addition to suspending metered parking. Details will follow through the Spring/Summer of 2024.

Were there any thoughts into potential traffic build-up on E. Main Street from vehicles trying to avoid the construction area plus the increased speeding from making a right onto E. Main Street from Broad Street?

Traffic should not be affected along E. Main Street and Broad Street. Plus, the traffic will slow speeds down during construction. PennDOT will certainly assess the traffic throughout the Borough to have traffic flow. PennDOT may make adjustments to traffic plans during construction as needed. PennDOT will have a full-time construction Superintendent on-site and anyone that needs to report traffic issues/concerns, should do so through the Borough Office and/or Borough Manager, who will forward concerns to PennDOT’s Superintendent.

Is the day-care center on W. Main Street at W. Northampton Street going to be removed?

Part of the land owned by the Learn-N-Play will be taken for use in reconstructing the W. Northampton Street and W. Main Street intersection. PennDOT has acquired necessary easements from the property owner. PennDOT is not removing the Learn-N-Play building as part of the re-alignment project.

Truck traffic coming south along State Route 512 and turning right onto Barrall Avenue, will these tractor trailers come down Old Forge Drive, if they are trying to avoid the downtown construction? Also, hearing it’s going to take 9 months for the bridge, what happens if this carries on for years, like the bridge replacement project in Kriedersville, this is a concern.

PennDOT certainly hopes that tractor trailer operators not find their way to Old Forge Drive as they shouldn’t. Again, this is a situation that PennDOT and the Borough will continue to monitor.

The major difference between the Bath Borough W. Northampton Street bridge replacement and the Kriedersville bridge replacement is size. The Kriedersville bridge project is more than twice the size of the W. Northampton Street bridge project. PennDOT does not believe the W. Northampton Street bridge replacement will take too long. The project is largely dependent on seasonal weather events.

Does PennDOT asses things like traffic flows in areas of construction, which transportation projects receive precedence over another, set priorities?

Yes, PennDOT does evaluate traffic flows and will make adjustments accordingly. PennDOT has had to balance labor and material costs as well. Plus, PennDOT partners (local asphalt or quarry plants) are experiencing labor issues and cannot run during off-peak hours, which creates delays in construction timelines.

After the W. Northampton Street bridge is replaced, will motorists be able to access State Route 248 from the West– making a left and continuing into Nazareth?

Yes, and even before construction is finished, motorists will have access to Nazareth through Bath.

Is there still the possibility of running a detour through East Allen Township near Airport Road to indicate the construction and try to avoid Bath? Also, coming into town from all directions? Just to provide advance notice to motorists as far out as possible?

PennDOT is looking into these concerns. PennDOT studies have found that motorists will not go out of their way to avoid the construction area. PennDOT recognizes there are no perfect solutions during the construction phase. PennDOT’s construction signage will be placed and posted with as much advanced notice as possible.

During the construction phase, will PennDOT be lowering speed limits on other state highways approaching the construction zone?

There are no plans to lower speed limits on surrounding state highways approaching the construction zone. Reducing speed limits on state highways are typically completed at the request of the local jurisdiction and after a traffic engineering study has been completed. The Borough does not anticipate lowering any speed limits along state highways at this time.